Payment conditions - Standard form - Year 2001 - For hull
value over
US $ / Euro 150,000.= - Payments at construction stage -
Condizioni di pagamento standard - Year 2001 -
Per scafi
dal valore inferiore US $ / Euro 150.000.= con pagamento a stadi di costruzione -
Condizioni di pagamento standard Anno 2001 - Per scafi oltre US $ / Euro 150.000.= con pagamento a stadi di costruzione -
Cash & Carry - The New Payment Conditions - Year 2001 -
For vessels value less than
US $ / Euro 150,000.= with 10% discount - No deposit - Payment on delivery
Le nuove Condizioni di pagamento Cash & Carry - Anno 2001
- Per imbarcazioni di valore
inferiore a US $ / Euro 150.000.= con 10% di sconto e senza deposito - Pagamento alla consegna -
2001 - Nouvelles conditions de paiement - 10% rabais -
Sans avance - Paiement à la livraison - Pour bateaux de valeur inférieure à
Euros 150.000.=
A - HULL with equipment installed.
Payment is related to the updated price list in US Dollars:
- 2001 - PRICE LIST - The updated price list -
Payment will be made as follows:
10% on order.
40% by opening an irrevocable Letter of Credit, confirmed by a
first class European or USA Bank, divisible and transferable with one year validity
or, at least, three months after the expected delivery time.
Partial payment allowed in case of order for several ships/ products.
L/C payments will be made as follows.
- 20% on opening
- 15 % at installation of propulsion engine/s.
- 5 % at launching.
Remaining- 50% - by issuing n. 5 mortgage promissory notes,
guaranteed by the ship property, and payable as follows:
10% - one year from the launching date.
10% - two years from launching date.
10% - three years from launching date.
10% - four years from launching date.
10% - five years from launching date.
SPECIAL CONDITIONS
1 - No interest rate will be charged on the promissory notes value.
2 - The cost of promissory notes and registration will be charged to Client.
3 - Client will provide an "ALL RISK" policy on the ship in favour of the Shipyard
covering the promissory notes value.
4 - Insurance Company should be approved by Shipyard.
5 - Copy of the insurance policy payments should be sent to Shipyard.
6 - Property or Flag changes should be previously authorized by Shipyard.
Vessel Flag will remain the Haitian’ up to the final settlemet.
7 - In case Shipowner does not pay one promissory notes within ten days from expiry date,
shipyard has the right to seize the ship as it is, with engines and
equipment installed included.
8 - Endorsements on the "International promissory notes" could be required by Institution
authorized to operate in the financial and guarantee field as Collateral Guarantor.
Guarantor' Company should be approved by Shipyard
9 - All payments will be done at first presentation of the certificates issued by the
Bureau Veritas - The standard Survey Authority - and within five working days
10 - All delays in payment will be "Cause of force majeure" and delivery date will be
postponed for a period of time wich shall not exceed the total of such
delays.
11 - BUILDER will give to BUYER and Insurance
Guarantee for all payments done prior delivery and covering the
VESSEL damages
during construction within 15 working days from each payment
12 - The Builder Insurance guarantee will cover the following payments:
- 15 % at installation of proulsion engine/s.
- 5 % at launching from the launching day up to the delivery date.
10 % on order
90 %by opening an irrevocable Letter of Credit, confirmed by a
first class European or USA Bank, divisible and transferable with one year validity
or, at least, three months after the expecxted delivery time.
Partial payment allowed in case of order for several ships/ products.
L/C payments will be made as follows:
30% on opening.
50% at installation.
10% at launching.
GUARANTEES
1 - Guarantees on engines and equipment are the same given by manufacturer.
2 - Hull is guaranteed for one year for all defects of construction.
3 - BUILDER will give to BUYER and Insurance
Guarantee for all payments done prior delivery and covering the
ENGINE/S damages
during construction within 15 working days from each payment
4 - The Builder Insurance guarantee will cover the following payments:
50% at Engine/s installation.
10% form launching day up to the Vessel delivery.
1 - Delivery time will start from the date of first payment acceptance.
2 - BUILDER will confirm in writing to BUYER the acceptance of the order after
verifying L/C text
D - DELIVERY PLACE: Miami
DELIVERY cost, Delivery Payment conditions, Transport Insurance,
etc:
Shipment cost to be paied prior delivery.
E - INSPECTION and SEA TRIALS
Construction is made in accordance to EC or to B.V.rules for merchant vessels.
Client / Inspector is allowed to test the vessel/boat prior delivery in accordance
to Construction Contract general conditions and terms.
Quality control during construction and sea test at delivery
could be carried-out by Bureau Veritas' Inspector at Client' charges.
TEST & TRIALS LOCATIONS - PROVA la TUA BARCA a.. - ESSAIS en MER : LOCALITES -
Pleasure craft price list - Listino prezzi delle barche da diporto
Work boats price list - Listino prezzi delle barche da lavoro
Ship plan legenda
Legenda piani generali
Welcome to the Shipyard
Miscellaneous production main list
Miscellaneous production price list
Lightbuoys - R.O.V. - Pipe inspection vehicle - etc.
Miscellaneous production price list
Condizioni di pagamento in Italiano - Per scafi oltre $ 40,000.=
Condizioni di pagamento in Italiano - Per scafi dal valore inferiore a $ 40,000.=